Progress on the construction of la Fontaine d’Ehden in Corseaux

La Fontaine d’Ehden continues to develop, with good progress on all buildings.
Technical visits to buildings A and B were successfully completed in April, validating the interior fittings with the purchasers. The partitions are now ready to be closed, enabling screed work to begin. With the completion of the roofs, the installation of railings and the wood cladding on the facades, the final face of the project is taking shape.
Insulation of the façade of Building C is complete, and interior work is progressing actively in preparation for the next visits with the future owners. The tiled roof is nearing completion.
As for Building D, the framework is now in place, marking the transition to the watertight phase at the end of April. The airtight phase will be reached as soon as the windows are installed at the end of the month.
The aim is to deliver the first apartments in autumn 2025. A milestone that the entire team is determined to achieve.
We look forward to seeing this major project take shape, and thank all those involved for their invaluable contribution.